Question 1

A project manager is preparing a communication plan. What is the most important factor to consider when determining the frequency of communications?

A) Project budget

B) Stakeholder communication needs

C) Project timeline

D) Availability of communication tools

Show Answer & Explanation

Correct Answer: B

Explanation: Stakeholder communication needs (Option B) are the most important factor when determining communication frequency, ensuring all stakeholders receive timely and relevant information. The project budget (Option A) and timeline (Option C) are considerations but secondary to stakeholder needs. Availability of communication tools (Option D) is logistical and should not dictate frequency. PMBOK® 7th Edition emphasizes tailoring communications to stakeholder needs.

Question 2

During the execution phase of a project, you notice that team members are unclear about their roles and responsibilities. What document should you refer to in order to clarify this?

A) Project Charter

B) Responsibility Assignment Matrix (RAM)

C) Project Scope Statement

D) Risk Register

Show Answer & Explanation

Correct Answer: B

Explanation: The Responsibility Assignment Matrix (RAM) is used to define the roles and responsibilities of project team members. The Project Charter (A) outlines the project objectives and high-level roles but not detailed responsibilities. The Project Scope Statement (C) defines the project scope, not roles. The Risk Register (D) is used to track risks, not roles and responsibilities.

Question 3

Which document formally authorizes a project and provides the project manager with the authority to apply resources to project activities?

A) Project Management Plan

B) Project Charter

C) Statement of Work

D) Business Case

Show Answer & Explanation

Correct Answer: B

Explanation: The 'Project Charter' formally authorizes a project and grants authority to the project manager. The 'Project Management Plan' details how the project will be executed, the 'Statement of Work' describes deliverables, and the 'Business Case' justifies the project. PMBOK® 7th Edition defines these documents.

Question 4

Which of the following is a key characteristic of a project?

A) It has a permanent team.

B) It produces a unique product, service, or result.

C) It is ongoing and repetitive.

D) It has no defined end date.

Show Answer & Explanation

Correct Answer: B

Explanation: A key characteristic of a project is that it produces a unique product, service, or result, as per PMBOK® 7th Edition. Projects are temporary endeavors (A and D are incorrect), and they are not ongoing and repetitive (C), which describes operations, not projects.

Question 5

What is the primary purpose of a project charter?

A) To define the detailed project schedule.

B) To formally authorize the existence of a project and provide the project manager with authority.

C) To outline the project communication plan.

D) To list all potential project risks.

Show Answer & Explanation

Correct Answer: B

Explanation: The correct answer is B. A project charter formally authorizes a project and provides the project manager with the authority to apply organizational resources to project activities. Option A is incorrect because the project schedule is detailed in the project management plan. Option C is part of the project management plan, not the charter. Option D is incorrect as risk listing is part of risk management planning. (PMBOK® 7th Edition, Chapter on Project Integration Management)

Question 6

What is the role of a project sponsor in a project?

A) To manage day-to-day project activities.

B) To provide resources and support for the project.

C) To develop the project team.

D) To create the project schedule.

Show Answer & Explanation

Correct Answer: B

Explanation: The correct answer is B. The project sponsor provides resources and support and is accountable for enabling success, as described in PMBOK® 7th Edition. Option A is the project manager's role. Option C is incorrect because team development is primarily the project manager's responsibility. Option D is incorrect because scheduling is part of project planning, typically led by the project manager.

Question 7

What is the primary purpose of a project charter?

A) To define detailed project requirements.

B) To formally authorize the project and provide the project manager with authority.

C) To track project progress against milestones.

D) To outline the project budget and financial resources.

Show Answer & Explanation

Correct Answer: B

Explanation: The project charter formally authorizes the project and gives the project manager authority to apply resources, as per PMBOK® Guide 7th Edition. Option A is incorrect as detailed requirements are part of the scope statement. Option C relates to project control and monitoring, not the charter. Option D is incorrect because while the charter may include high-level budget information, its primary purpose is authorization.

Question 8

You notice that a key deliverable has not been met according to the project schedule. What should be your first step?

A) Update the project schedule to reflect the delay.

B) Conduct a root cause analysis to understand why the deliverable was missed.

C) Inform the project sponsor immediately.

D) Reassign the task to a more capable team member.

Show Answer & Explanation

Correct Answer: B

Explanation: Option B is correct as conducting a root cause analysis helps identify the underlying issues causing the delay. Option A is incorrect as it addresses the symptom rather than the cause. Option C is premature without understanding the issue. Option D may not resolve the underlying problem. Refer to PMBOK® 7th Edition, Schedule Management.

Question 9

A project manager is using a work breakdown structure (WBS) to manage a project. What is the primary benefit of using a WBS?

A) It helps in identifying project risks.

B) It provides a detailed project schedule.

C) It breaks down the project into manageable components.

D) It ensures all project stakeholders are identified.

Show Answer & Explanation

Correct Answer: C

Explanation: The primary benefit of a WBS (C) is breaking down the project into manageable components, facilitating better planning and control. Identifying risks (A), scheduling (B), and stakeholder identification (D) are separate project management activities.

Question 10

Which of the following best describes the role of a project sponsor?

A) To manage day-to-day project activities

B) To provide resources and support for the project and ensure it is aligned with business objectives

C) To execute project tasks and report to the project manager

D) To create the project schedule and budget

Show Answer & Explanation

Correct Answer: B

Explanation: The correct answer is B. The project sponsor provides resources and support, and ensures alignment with business objectives (PMBOK® 7th Edition, Chapter on Stakeholder Performance Domain). Option A is incorrect because managing day-to-day activities is the project manager's role. Option C is incorrect because executing tasks is typically the role of team members. Option D is incorrect because creating the schedule and budget is part of the project manager's responsibilities.

Ready to Accelerate Your CAPM Preparation?

Join thousands of professionals who are advancing their careers through expert certification preparation with FlashGenius.

  • ✅ Unlimited practice questions across all CAPM domains
  • ✅ Full-length exam simulations with real-time scoring
  • ✅ AI-powered performance tracking and weak area identification
  • ✅ Personalized study plans with adaptive learning
  • ✅ Mobile-friendly platform for studying anywhere, anytime
  • ✅ Expert explanations and study resources
Start Free Practice Now

Already have an account? Sign in here

About CAPM Certification

The CAPM certification validates your expertise in project management fundamentals and core concepts and other critical domains. Our comprehensive practice questions are carefully crafted to mirror the actual exam experience and help you identify knowledge gaps before test day.