Updated for the PMP® Exam Content Outline in effect since July 9, 2026
Free PMP Exam Simulator 2026 — Practice Every Question Type
Try every question format on the current PMP exam, including Case & Scenario Sets and Graphic-Based questions — not just read about them. Six modules cover each format, then a mixed simulation mirrors real exam pacing.
90 practice questions · No account required · Progress saved automatically · Last updated November 2026
The PMP exam at a glance
- Questions: 180 (170 scored, 10 unscored pretest)
- Time: 240 minutes
- Breaks: Two 10-minute breaks
- Content outline: PMI 2026 Examination Content Outline, aligned with the PMBOK Guide 8th Edition
PMP question types
Case & Scenario Sets (New in 2026)
One detailed scenario followed by several linked questions that build on the same situation, testing how you reason through a project end to end.
Graphic-Based Questions (New in 2026)
Read a chart, diagram or dashboard, then answer questions based on what the visual tells you.
Point & Click (Enhanced)
Click the correct zone on an image, with richer images and interactive hotspots.
Enhanced Matching (Enhanced)
Pair items across two columns with drag-and-drop.
Multiple Response (Standard)
Select every answer that applies. Partial credit is not given, so precision matters.
Pull-Down List (Standard)
Fill blanks in a scenario by choosing the right option from a dropdown list.
PMP Sample Questions with Answers
One worked example per format, taken from the lab. Open each to see the answer and explanation.
Case & Scenario Set · Business Environment
Riverside Platform Migration
A financial services firm is migrating a legacy platform. Regulatory reporting modules must follow a predictive approach for audit traceability, while the new customer dashboard is built in two-week agile sprints. Six weeks in, the sponsor asks the project leader to justify continued funding by showing the value delivered so far, not just percent complete.
What should the project leader present to answer the sponsor's request?
- A Gantt chart showing percent complete for every activity
- A summary of benefits realized and increments accepted so far, mapped to the business case
- The team's velocity chart for the last three sprints only
- A risk register updated with current open items
Show answer and explanation
Correct answer: A summary of benefits realized and increments accepted so far, mapped to the business case
The sponsor asked about value delivered, not task completion. Mapping accepted increments back to the business case answers whether the funding remains worthwhile.
Why is a hybrid approach appropriate here rather than a single method?
- Hybrid always finishes faster than either method alone
- Predictive suits the fixed compliance requirements; agile suits the evolving dashboard scope
- PMI requires hybrid delivery for any project touching regulated data
- It reduces the number of stakeholders that must be engaged
Show answer and explanation
Correct answer: Predictive suits the fixed compliance requirements; agile suits the evolving dashboard scope
Hybrid is chosen when different parts of a project have genuinely different characteristics: fixed audit-driven work suits predictive, evolving scope suits agile.
The sponsor is still unconvinced value is being delivered. What is the best next step?
- Escalate to the PMO and request the sponsor be replaced
- Increase reporting frequency to daily status emails
- Facilitate a session to realign on the benefits framework and how increments map to it
- Pause the agile workstream until the audit is complete
Show answer and explanation
Correct answer: Facilitate a session to realign on the benefits framework and how increments map to it
The root issue is a shared-understanding gap about what counts as value. A facilitated realignment addresses that, keeping the sponsor as a partner.
Graphic-Based · Process
Network diagram
The diagram shows activities A (2 days), B (5 days), C (7 days), D (3 days) and F (2 days), connected in two paths: A → B → D → F and A → C → D → F.
What is the total project duration shown in this diagram?
- 12 days
- 13 days
- 14 days
- 16 days
Show answer and explanation
Correct answer: 14 days
Project duration equals the length of the critical path. A→C→D→F is 2+7+3+2 = 14 days.
Multiple Response · Business Environment
Enterprise Environmental Factors
Which of the following are Enterprise Environmental Factors (select all that apply)?
- Government regulations
- The project's risk register
- Marketplace conditions
- The schedule baseline
- Organizational culture
Show answer and explanation
Correct answer: Government regulations; Marketplace conditions; Organizational culture
EEFs are external or organizational conditions outside the team's control. The risk register and schedule baseline are project documents the team creates.
Enhanced Matching · Process
Earned value terms
Match each earned value term to what it measures.
- Earned Value (EV)
- Planned Value (PV)
- Actual Cost (AC)
- Cost Performance Index
Show answer and explanation
Correct answer: EV → Budgeted cost of work actually completed; PV → Budgeted cost of work scheduled to date; AC → Actual cost incurred for work completed; CPI → Cost efficiency of work performed (EV ÷ AC)
EV is completed work valued at budget, PV is the baseline spend planned by now, AC is what was actually spent, and CPI compares EV to AC to show cost efficiency.
Pull-Down List · Process
Critical-path slippage
When a critical-path activity slips with no float, the team can [blank 1] the schedule by [blank 2], accepting [blank 3].
- Blank 1: compress / ignore / baseline
- Blank 2: fast-tracking or crashing / removing scope silently / waiting longer
- Blank 3: added cost or risk / guaranteed savings / no trade-offs
Show answer and explanation
Correct answer: compress; fast-tracking or crashing; added cost or risk
Slippage on the critical path calls for compression. Fast-tracking and crashing are the two compression techniques, and both trade time for cost or risk.
PMP Domain Weights: Current Exam vs. 2021 Exam
Business Environment more than tripled when the new exam launched on July 9, 2026.
| Domain | 2021 Exam | Current Exam (since July 9, 2026) |
| People | 42% | 33% |
| Process | 50% | 41% |
| Business Environment | 8% | 26% |
The three domains are unchanged, but Business Environment now makes up about a quarter of the exam, and AI and sustainability are testable topics.
PMP Mock Exam — Frequently Asked Questions
What changed on the PMP exam in July 2026?
Since July 9, 2026, the PMP exam follows PMI's 2026 Examination Content Outline, aligned with the PMBOK Guide 8th Edition. The three domains stayed the same, but Business Environment rose from 8% to 26% of the exam, while People fell to 33% and Process to 41%. The exam also added Case and Scenario Sets and Graphic-Based questions, and expanded AI and sustainability as testable topics.
What question types are on the PMP exam?
There are two formats new in 2026, Case and Scenario Sets and Graphic-Based questions, plus enhanced Matching and Point-and-Click items that support images and drag-and-drop. Standard formats such as Multiple Response and Pull-Down List continue.
How many questions are on the PMP exam, and how long is it?
The exam has 180 questions: 170 scored plus 10 unscored pretest questions that you can't tell apart from the rest. You have 240 minutes, with two 10-minute breaks. The 2021 exam had 5 pretest questions and 230 minutes.
I studied with pre-2026 material. What should I change?
The three domains are the same, so most People and Process study still applies. Spend more time on Business Environment, which is now about a quarter of the exam: governance, compliance, benefits realization, organizational change and sustainability. Then practice the case-set and graphic-based formats so the new layouts don't slow you down on exam day.
Is this PMP practice test free?
Yes. Every question-type module and the mixed-format simulation are free to use, with no account required. Your progress is saved automatically so you can pick up where you left off.