Free PMP Practice Exam for the July 2026 Outline
Start answering below: 10 questions in the same 3/4/3 mix as the exam's domain weights, with no signup. You get your score by domain and an explanation for every question.
Last updated November 6, 2026.
10 Free PMP Practice Questions with Answers
Question 1: People
Two lab managers on a predictive pathology-lab move signed a resolution for sharing one analyzer: mornings for one lab, afternoons for the other, with unresolved breaches going to the sponsor. One manager has overrun into the afternoon on six days, and the project manager has raised this with that manager twice. Test schedules are now slipping. What should the project manager do next?
- Lease a second analyzer with contingency reserve to remove the source of the dispute
- Move the affected lab's tests to weekends to protect the overall test schedule
- Meet both of the lab managers again to reconfirm the terms of the resolution
- Escalate the breaches to the sponsor, as the signed resolution provides
Correct answer: D. D is correct because the agreed strategy names this step, and two direct attempts have failed while the schedule slips. A is incorrect because this spends funds on a problem the managers already resolved on paper, and no one has approved that spend. B is incorrect because this makes the lab that kept the agreement absorb the cost of the breach, and it leaves the breach unaddressed. C is incorrect because the terms are clear and signed, and more meetings would delay the step that both managers agreed to. Exam outline: People, Task 2 (Manage conflicts).
Question 2: People
An agile team depends on a shared platform group to expose a new interface. The platform head has no reporting line to the project and has twice said the request isn't a priority. The project manager has just learned that the platform head's annual goal is to retire an old interface, and the new interface would let its three largest users move off it. What is the best next step?
- Escalate to the chief technology officer to have the request placed first in the group's queue
- Have the team build its own version of the interface so that it no longer needs the group
- Ask the product owner to drop the feature from the product backlog and look for other value
- Show the platform head how the interface helps meet the retirement goal, and ask again
Correct answer: D. D is correct because with no authority over the platform head, the project manager's best lever is a shared interest that has just come to light. A is incorrect because the new information gives a better option to try first, and forcing priority may damage the working relationship. B is incorrect because this duplicates a shared platform's role and adds to the older interfaces that the group is trying to retire. C is incorrect because this gives up on the work before trying the fresh argument for it, and the value may be high. Exam outline: People, Task 4 (Engage stakeholders).
Question 3: People
A clinic network's predictive records-system replacement has four communication needs:
- Two department heads disagree on cutover timing and must reach a decision.
- All staff must be told about next month's system downtime.
- Training guides and past release notes must be available when staff need them.
- A weekly status summary goes to the list named in the communications plan.
Which option best matches each need to a communication method?
- 1 Pull; 2 Push; 3 Interactive; 4 Interactive
- 1 Push; 2 Interactive; 3 Push; 4 Pull
- 1 Interactive; 2 Push; 3 Pull; 4 Push
- 1 Interactive; 2 Pull; 3 Push; 4 Interactive
Correct answer: C. C is correct because a disagreement needs two-way discussion, downtime and status notices are sent to named recipients, and staff consult guides when they need them. A is incorrect because the department heads can't reach a decision by looking up material, and guides are reference content staff use on demand. B is incorrect because a one-way message won't settle a disagreement, and a live session isn't needed to tell all staff about downtime. D is incorrect because posting downtime for staff to find risks missing people who must know, and a status summary sent to a list doesn't need a live exchange. Exam outline: People, Task 8 (Plan and manage communication).
Question 4: Process
During a final check of the consolidated plans for a predictive cold-storage warehouse, the project manager reviews these milestones.
| Plan | Milestone | Week | Needs first |
|---|
| Procurement | Refrigeration units on site | 24 | Order placed, week 6 |
| Construction | Insulated panels complete | 22 | Steel frame, week 14 |
| Mechanical | Refrigeration units installed | 26 | Units on site, panels complete |
| Commissioning | Cold-room test | 27 | Power connection live |
| Utility | Power connection live | 30 | Application, week 8 |
Which milestone needs correcting?
- Refrigeration units installed, because it allows just two weeks after the units arrive on site
- Power connection live, because 22 weeks is too long to wait after the application in week 8
- Insulated panels complete, because the panels finish two weeks ahead of the units arriving
- Cold-room test, because the power it needs goes live three weeks after it is scheduled
Correct answer: D. D is correct because commissioning in week 27 can't run on a power connection that arrives in week 30, and the plans show the gap when compared. A is incorrect because those two predecessors finish in weeks 24 and 22, so installation in week 26 follows them, and nothing shows two weeks is too short. B is incorrect because a long utility lead time is not itself a plan error, and nothing shows that it could be shorter. C is incorrect because panels finishing first is what the mechanical work needs, so this order is sound and not a gap. Exam outline: Process, Task 1 (Develop an integrated project management plan and plan delivery).
Question 5: Process
A logistics firm's hybrid project installs tracking units on 600 trucks under a predictive plan, while an agile team builds route analytics. The analytics team has only synthetic data, and installs are scheduled by depot convenience. Fitting the first 100 units on the busiest routes would cost nothing extra and give real data months earlier. Which decision best supports early value?
- Ask the depots to volunteer trucks, so that the install order reflects each depot's convenience
- Hold the analytics releases until the install work reaches its final completion milestone
- Sequence the first 100 installs on the busiest routes so analytics works from real data sooner
- Have the analytics team keep using synthetic data until all 600 trucks have their units
Correct answer: C. C is correct because this costs nothing extra and lets the agile team deliver value from real data months earlier than the current order. A is incorrect because that repeats the current basis for the order, which is what keeps the busiest routes from supplying data early. B is incorrect because nothing requires analytics to wait for the whole fleet, so this gives up value that a partial fleet can support. D is incorrect because this delays the real data that would let analytics show value, though part of the fleet could supply it months earlier. Exam outline: Process, Task 3 (Help ensure value-based delivery).
Question 6: Process
A project team on a predictive road-widening job shows this month 6 status. The sponsor says the job is doing very well because it has spent $200,000 less than planned.
| Measure | Value |
|---|
| BAC | $1,200,000 |
| PV | $600,000 |
| EV | $480,000 |
| AC | $400,000 |
| CV / SV | +$80,000 / -$120,000 |
| CPI / SPI | 1.20 / 0.80 |
What should the project manager tell the sponsor?
- The job is on budget and on schedule, as the CPI and SPI average out to exactly 1.00
- The job is over budget and behind schedule, as both EV and AC are below the planned value
- The job is $200,000 under budget, so that amount is available to return to the sponsor
- Low spending partly reflects less work done: cost is favorable, but the job is behind schedule
Correct answer: D. D is correct because AC is below PV partly because EV is $120,000 short of plan, so only $80,000 of the gap is true cost saving. A is incorrect because averaging the two indexes hides the fact that the job is ahead on cost efficiency and behind on schedule. B is incorrect because being below PV doesn't indicate overspending, and EV is above AC, so cost performance is favorable. C is incorrect because comparing AC with PV mixes cost and schedule, and the real cost variance is $80,000, with a schedule shortfall too. Exam outline: Process, Task 6 (Plan and manage finance).
Question 7: Process
Case: dairy processing plant upgrade. A regional dairy cooperative is upgrading a processing plant under a predictive plan with an approved schedule baseline. The plant stays in service throughout, so the operations division controls when process lines can go offline. Pasteurizer installation needs its line offline for its whole duration and can't begin until civil works finish. Durations are in weeks, and the project finishes at the end of week 20.
| Activity | Predecessors | Duration | Total float |
|---|
| Site preparation | Start | 3 | 0 |
| Civil works | Site preparation | 8 | 0 |
| Pipe fabrication | Site preparation | 5 | 3 |
| Pasteurizer installation | Civil works, Pipe fabrication | 6 | 0 |
| Controls installation | Pipe fabrication | 4 | 5 |
| Commissioning | Pasteurizer installation, Controls installation | 3 | 0 |
Development: In week 6, the fabricator reports that pipe fabrication will finish at the end of week 10, two weeks later than planned. Nothing else has changed. What should the project manager do next?
- Overlap pipe fabrication with pasteurizer installation to recover the two lost weeks
- Keep the week 20 finish, and tell the controls team it starts two weeks later
- Request a baseline change that moves the project finish date out to week 22
- Crash civil works by two weeks to protect the planned week 20 finish date
Correct answer: B. B is correct because pipe fabrication has 3 weeks of float, so a 2-week slip holds the finish, but controls installation follows it and now starts after week 10. A is incorrect because pasteurizer installation can't start before civil works finish in week 11, and the two lost weeks don't need recovering. C is incorrect because the critical path is unchanged at 20 weeks, so the finish date hasn't moved and there's nothing to rebaseline. D is incorrect because the slip stays within float, so the finish date isn't at risk, and this would spend money for no benefit. Exam outline: Process, Task 8 (Plan and manage schedule).
Question 8: Business Environment
A retailer's hybrid packaging redesign has agile design work and a fixed supply contract. The contract requires the supplier to hold a current recycled-content certificate, and the retailer's sustainability policy makes that certificate a condition of the shelf claim. During a vendor check, the project manager finds the certificate expired two months ago. Two lots have shipped since then and are in the warehouse. What is the best next step?
- Accept the lots as they are, since the supplier was certified when the contract was signed
- Hold the two lots, and require the current certificate before they can carry the claim
- Remove the recycled-content claim from every store's shelf labels across the whole chain
- Terminate the supplier's contract for breach, and start sourcing packaging from elsewhere
Correct answer: B. B is correct because the certificate is the stated condition, and the lots are still in the warehouse, so a hold prevents an unsupported claim. A is incorrect because the contract requires a current certificate, so its status at signing doesn't cover these two lots. C is incorrect because earlier lots may be properly certified, so this is broader than the facts support and gives up value needlessly. D is incorrect because termination is far out of proportion before the supplier has had any chance to produce a valid certificate. Exam outline: Business Environment, Task 2 (Plan and manage project compliance).
Question 9: Business Environment
On a predictive laboratory information system project, a change to a result-flagging rule has been implemented and tested. The team wants it shown as closed on Friday's steering dashboard. Updating the traceability matrix and validation protocol, both controlled documents for this validated system, will take until next Wednesday. How should the project manager handle Friday's report?
- Mark the change closed on Friday, and track the documents as a separate follow-up action
- Ask the quality lead for a one-time waiver so the dashboard can show the change closed
- Report the change as implemented with documents open, and close it next Wednesday
- Move the steering review back to Wednesday so the dashboard can show the change closed
Correct answer: C. C is correct because a change to a validated system isn't complete until its controlled documents match what was built, and this gives steering an accurate status without delaying anything. A is incorrect because the controlled documents are part of completing the change, so showing it closed would make the dashboard wrong. B is incorrect because a cleaner dashboard is not a reason to waive a control on validated documents when accurate reporting is available. D is incorrect because holding up a governance meeting for one status entry is out of proportion when the true status can simply be reported. Exam outline: Business Environment, Task 3 (Manage and control changes).
Question 10: Business Environment
The risk plan for a predictive clinic-network expansion says: score 0.25 or above needs an owner and an active response; 0.10 to 0.24 goes on the watch list; below 0.10 is accepted.
| ID | Risk | Prob. | Impact | Score | Handling |
|---|
| R1 | Nurse licensing delay | 0.5 | 0.6 | 0.30 | Mitigate, owner named |
| R2 | Lab equipment recall | 0.3 | 0.9 | 0.27 | Watch list |
| R3 | Minor fit-out rework | 0.5 | 0.2 | 0.10 | Watch list |
| R4 | Signage reprint | 0.4 | 0.1 | 0.04 | Accepted |
| R5 | Landlord access delay | 0.7 | 0.3 | 0.21 | Watch list |
Which entry should the project manager correct?
- R4, whose score means it should be on the watch list
- R5, whose probability is the highest of the five entries
- R2, which is handled below the level its score requires
- R3, whose score could justify simply accepting the risk
Correct answer: C. C is correct because 0.27 is above the 0.25 line, so it needs an owner and an active response and can't stay on the watch list. A is incorrect because 0.04 is below 0.10, so the plan treats it as accepted, as shown. B is incorrect because at 0.21 it falls in the watch-list band, and the plan uses the score to decide handling and not probability. D is incorrect because 0.10 is the bottom of the watch-list band, so the watch list is what the plan requires. Exam outline: Business Environment, Task 5 (Plan and manage risk).
Practice by PMP Domain
- People practice questions (33% of the exam): People is 33% of the exam. It covers the shared vision, conflict, team leadership, stakeholder engagement and expectations, knowledge transfer and communication.
- Process practice questions (41% of the exam): Process is 41% of the exam, the largest domain. It covers integrated planning, scope, value-based delivery, resources, procurement, finance, quality, schedule, status and closure.
- Business Environment practice questions (26% of the exam): Business Environment grew from 8% to 26% of the exam. It covers governance, compliance, change control, issues, risk, continuous improvement, organizational change and the external environment.
PMP Exam at a Glance
- 180 questions (170 scored, 10 pretest)
- 240 min with two 10-minute breaks
- 40 / 60 % predictive vs agile and hybrid
- 3 domains: 33% / 41% / 26%
Old vs New PMP Exam
| Item | Before July 2026 | Now |
|---|
| People | 42% | 33% |
| Process | 50% | 41% |
| Business Environment | 8% | 26% |
| Exam time | 230 minutes | 240 minutes |
| New question types | None | Case or Scenario, and Graphic-Based |
Questions in Our Bank for Each of PMI's 26 Tasks
| Task | PMI outline task | Domain | Questions |
|---|
| 1.1 | Develop a common vision | People | 30 |
| 1.2 | Manage conflicts | People | 45 |
| 1.3 | Lead the project team | People | 50 |
| 1.4 | Engage stakeholders | People | 45 |
| 1.5 | Align stakeholder expectations | People | 30 |
| 1.6 | Manage stakeholder expectations | People | 30 |
| 1.7 | Help ensure knowledge transfer | People | 22 |
| 1.8 | Plan and manage communication | People | 45 |
| 2.1 | Develop an integrated project management plan and plan delivery | Process | 55 |
| 2.2 | Develop and manage project scope | Process | 30 |
| 2.3 | Help ensure value-based delivery | Process | 45 |
| 2.4 | Plan and manage resources | Process | 25 |
| 2.5 | Plan and manage procurement | Process | 40 |
| 2.6 | Plan and manage finance | Process | 40 |
| 2.7 | Plan and optimize quality of products/deliverables | Process | 35 |
| 2.8 | Plan and manage schedule | Process | 40 |
| 2.9 | Evaluate project status | Process | 39 |
| 2.10 | Manage project closure | Process | 20 |
| 3.1 | Define and establish project governance | Business Environment | 35 |
| 3.2 | Plan and manage project compliance | Business Environment | 35 |
| 3.3 | Manage and control changes | Business Environment | 35 |
| 3.4 | Remove impediments and manage issues | Business Environment | 35 |
| 3.5 | Plan and manage risk | Business Environment | 45 |
| 3.6 | Continuous improvement | Business Environment | 15 |
| 3.7 | Support organizational change | Business Environment | 17 |
| 3.8 | Evaluate external business environment changes | Business Environment | 17 |
How These Questions Were Built
The bank has 900 questions, split to follow the outline: People 297, Process 369 and Business Environment 234. Each question is mapped to one of the outline's 26 tasks, as the table above shows.
About 40% of the questions use a predictive setting, matching the outline. The rest are split between agile and hybrid. PMI doesn't publish that split, so an even split is our assumption.
Questions were drafted with AI assistance, then checked in a separate review pass against the outline task and the reasoning for each answer.
The real exam includes interactive formats. Our questions are all single-answer, so case items repeat the shared scenario, graphics appear as tables, and matching appears as answer sets. To try the interactive formats, use the free PMP Format Lab.
- Situational: 401
- Exhibit (table or chart data): 183
- Matching adapted to one answer: 134
- Case with a shared scenario: 97
- Concept and calculation: 85
Sources: PMI's PMP certification page and Examination Content Outline. Try the PMP Format Lab or the PMP cheat sheet.
PMP Practice Exam FAQ
What is on the PMP exam now?
The exam has 180 questions, of which 170 are scored and 10 are unscored pretest questions. You get 240 minutes and two 10-minute breaks. The domains are People (33%), Process (41%) and Business Environment (26%).
What changed with the July 2026 PMP outline?
Business Environment grew from 8% to 26%, while People fell from 42% to 33% and Process fell from 50% to 41%. Exam time went from 230 to 240 minutes. The outline also lists Case or Scenario and Graphic-Based as new question types.
How many agile and hybrid questions are on the PMP exam?
PMI's outline says about 40% of items represent predictive approaches. The other 60% or so are adaptive/agile and hybrid, and PMI doesn't publish how those two split.
Are these real PMP exam questions?
No. They are original practice questions written for the 26 tasks in PMI's outline. FlashGenius is not affiliated with or endorsed by PMI.
Do these questions use the new PMP formats?
They practice the same skills in single-answer form: case items repeat the shared scenario, graphics appear as tables, and matching appears as answer sets. The free PMP Format Lab lets you try the interactive formats.
How many PMP questions can I practice for free?
You can answer 40 questions with no signup: the 10 mixed questions on this page and 10 for each of the three domains. A free account adds 10 practice questions a day, and Premium opens the full 900-question bank and 180-question mock exams.
Does my score here predict whether I'll pass?
No. It shows your accuracy on this set and which domain to work on next. PMI doesn't publish a passing score, and a short set can't predict an exam result.
FlashGenius is not affiliated with or endorsed by PMI. PMP and PMBOK are marks of the Project Management Institute. These are original practice questions, not questions from the real exam. Your score here is practice accuracy, not a PMI result or a pass prediction.