Free PMP Schedule Management Practice Test 2026 — Project Management Professional Questions

This free PMP Schedule Management practice test covers PMI Knowledge Area 3 — schedule management, including CPM, schedule compression, resource leveling, and PDM diagrams. Each question includes a detailed explanation grounded in the PMBOK Guide and PMP Examination Content Outline.

Key Topics in PMP Schedule Management

6 Free PMP Schedule Management Practice Questions with Answers

Sample Question 1 — Project Schedule Management

You're managing a software development project using Agile. During the sprint review, stakeholders identify a critical feature missing from the sprint deliverable. How should you best address this?

  1. A. Ignore the feedback, as the sprint is already complete.
  2. B. Immediately add the feature to the next sprint, regardless of capacity.
  3. C. Assess the impact, prioritize the feature, and discuss adding it to the backlog or future sprint with stakeholders. (Correct answer)
  4. D. Blame the development team for missing the requirement.

Correct answer: C

Explanation: Option C aligns with Agile principles by acknowledging stakeholder feedback and incorporating it through proper prioritization and backlog management. Options A and D are unprofessional and disregard stakeholder needs. Option B disregards sprint capacity and potentially impacts the project's timeline and quality.

Sample Question 2 — Project Schedule Management

A project is experiencing significant delays due to unforeseen technical challenges. The original schedule was created using a predictive approach. What is the BEST approach to revise the schedule?

  1. A. Ignore the delays and continue as planned.
  2. B. Add the extra time to the end of the project without analysis.
  3. C. Re-evaluate the remaining tasks, identify impacted dependencies, and create a revised schedule using critical path analysis and updated task durations. (Correct answer)
  4. D. Blame the technical team and push for them to accelerate the work.

Correct answer: C

Explanation: Option C is the most effective as it addresses the root cause (technical challenges) and uses project management techniques (critical path analysis) to create a realistic revised schedule. Options A and B disregard the delays and are unprofessional. Option D is not a problem-solving approach.

Sample Question 3 — Project Schedule Management

Your project is using a hybrid approach (Agile sprints within a Waterfall framework). During a sprint, a critical dependency on a deliverable from another team is delayed. How should you respond?

  1. A. Ignore the delay and hope it resolves itself.
  2. B. Immediately escalate the issue to senior management, demanding action.
  3. C. Communicate with the dependent team, understand the impact, and collaborate on mitigation strategies, potentially adjusting sprint goals or the overall project schedule. (Correct answer)
  4. D. Proceed with the sprint as planned, accepting the delay in the project's completion date.

Correct answer: C

Explanation: Option C promotes proactive communication and collaboration, key elements of effective project management in any methodology. Options A and B are passive or aggressive and ineffective. Option D ignores the impact on the overall project schedule.

Sample Question 4 — Project Schedule Management

A critical path activity is unexpectedly delayed. What's the FIRST step you should take?

  1. A. Immediately inform senior management of the delay.
  2. B. Assess the impact of the delay on the project completion date and other activities. (Correct answer)
  3. C. Blame the team responsible for the delay.
  4. D. Crash the schedule by adding more resources without careful consideration.

Correct answer: B

Explanation: Before escalating or taking drastic action, understanding the impact is crucial. Option B allows for informed decision-making. Options A and C are premature and unproductive; Option D is risky without proper assessment.

Sample Question 5 — Project Schedule Management

You're using Earned Value Management (EVM) to track a project. You find that the schedule performance index (SPI) is 0.8. What does this indicate?

  1. A. The project is ahead of schedule.
  2. B. The project is on schedule.
  3. C. The project is behind schedule. (Correct answer)
  4. D. The project's cost performance is poor.

Correct answer: C

Explanation: An SPI of less than 1 indicates that the project is behind schedule. The SPI is the ratio of earned value to planned value.

Sample Question 6 — Project Schedule Management

During project execution, a major stakeholder requests a significant scope change that would impact the project schedule. What's the appropriate first action?

  1. A. Immediately implement the change.
  2. B. Inform the stakeholder that the change is impossible.
  3. C. Evaluate the impact of the change request on the project schedule, cost, and resources using a formal change request process. (Correct answer)
  4. D. Delay the decision until the end of the current phase.

Correct answer: C

Explanation: Following a formal change control process is crucial for managing scope changes. Option C ensures proper evaluation and documentation. Options A and D are inappropriate responses; Option B is too inflexible.

About the PMP / Project Management Professional Exam

Other PMP Practice Domains

Start the free PMP Schedule Management practice test now | 10-question quick start | All PMP domains